Looking for:

View the Critical Path in Project – Instructions – TeachUcomp, Inc..

Click here to Download

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
These instructions are specific to Project By default, Project displays only one critical path, the path that affects the plan’s finish date. Tip: If you bring in the finish dates of the critical path and another series of tasks does not overtake it, then you can successfully bring in the finish date of the project.
 
 

 

Show the critical path of your project in Project – Critical Path Tool features include:

 

Viewing these tasks with slack helps alert you to tasks that are becoming critical while you still have some buffer. In the Tasks are critical if slack is less than or equal to list, enter the number of days under which a task will be considered critical.

When you display the project’s critical path , Project shows only a single, overall critical path, which is the only critical path that controls the project’s finish date.

However, you can set up your plan so that you can also see an additional critical path for each independent network or each series of tasks. You might find this useful for keeping track of each of the subprojects within a master project, or of each phase or milestone of a project that is divided into multiple phases. By knowing and tracking the critical path for your project, as well as the resources that are assigned to each critical task, you can identify the tasks that can affect your project’s finish date and thus discover whether your project will finish on schedule.

Learn more by reading Manage your project’s critical path. To verify that adjustments that you make to the project plan don’t adversely affect the critical path, you can review the critical path and critical tasks in any of several ways. Note: By default, Project does not display a project’s critical path. To display all tasks again, select All Tasks in the Filter list on the toolbar.

You can also group all critical tasks together. On the Project menu, point to Group by , and then select Critical. Follow the instructions in the Gantt Chart Wizard to format the critical path. By default, the Gantt chart bars and link lines for critical tasks are displayed in red. This format change overrides any direct formatting changes previously made to bar styles or to individual bars.

Note that this formatting of critical tasks applies only to the current Gantt Chart view in the current file. To use the same formatting in another file, you can use the Organizer Tools menu to copy formatted Gantt Charts to other files. On the Tools menu, choose Options , select the Calculation tab, and then select the Calculate multiple critical paths check box.

Important: This procedure is only effective in a consolidated project. If you don’t have a consolidated project, you must first create one. On the Tools menu, choose Options , select the Calculation tab, and then select the Inserted projects are calculated like summary tasks check box. This is a project-level setting. All projects inserted into this project will be calculated like summary tasks. In Project , a critical task has zero days of slack float.

However, you can change this default value and define a task as critical that has, for example, one or two days of slack. On the Tools menu, choose Options , and then select the Calculation tab. In the Tasks are critical if slack is less than or equal to box, enter the maximum amount of slack, in days, that you want to use to define critical tasks. If you want this value to be the default value for all of your projects, choose Set as Default.

To learn how to find a task’s slack, see Show slack in your project. For instructions about changing a task’s slack, see Set lead or lag time float between tasks. Tip: To change the sensitivity of critical tasks, on the Tools menu, choose Options. On the Calculation tab, under Tasks are critical if slack is less than or equal to , specify the number of days under which a task will be considered critical. In your project, select Timeline.

Select Filters. Turn on the toggle Show Critical Path. When Show Critical Path is on, you’ll see the critical path for your project highlighted red in the timeline. Manage your project’s critical path.

View and track scheduling factors. In a typical project, many tasks have some slack and can therefore be delayed a bit without delaying other tasks or affecting the project finish date. As you modify tasks to resolve overallocations, adjust costs, or revise scope, be aware of the critical tasks and that changes to them will affect your project finish date.

Critical tasks make up the schedule’s critical path. A task stops being critical when it’s completed, because it can no longer affect the completion of successor tasks or the project finish date. Projectdefines critical tasks as those that have no slack float. However, you can change when a task becomes critical.

For example, you can make a task critical if it has one or two days of slack. This is helpful if you want to be alerted to tasks becoming critical when you still have a day or two of buffer. Slack is determined by the early finish and late finish dates of the tasks in your schedule. An early finish date is the earliest date that the task could finish, based on its start date and scheduled duration.

A late finish date is the latest date that the task can finish without delaying the project finish. The difference between early finish and late finish dates determines the amount of slack. For critical path tasks tasks that have no slack , the early finish and late finish dates are identical.

If you want your project to have an earlier finish date, you must bring in the dates of your critical path tasks. This is also known as crashing a project. To do this, you can:. Break a critical task into smaller tasks that can be worked on at the same time by different resources. Note: If you bring in the dates of your critical path, a different series of tasks could become the new critical path.

There is always one overall critical path for any project schedule. The new critical path would then become the series of tasks you track more closely to make sure the finish date you want. Tip: If you bring in the finish dates of the critical path and another series of tasks does not overtake it, then you can successfully bring in the finish date of the project.

Show slack in your project. Set a task start or finish date constraint for a task. Change a duration for a task on the critical path. Link tasks in a project. Add lead or lag time to a task. Adjust the time a work resource spends on a task. The project is considered complete when the last task in the critical path is finished. The critical path is continuously calculated by Microsoft Project and can change as tasks are modified or updated.

It is worth noting that this calculation is purely an estimate. Despite this, the critical path gives project managers a good idea of where to focus attention. To see Critical Paths in action, please watch the following video tutorial. The critical path is automatically applied to all projects.

It is, however, essential to be able to identify the critical path and the tasks contained within. This view will allow you to see the total slack for tasks in the project in the last column. You can see the critical tasks on the Gantt Chart if you have applied the Schedule view switch back to Gantt Chart view and clear the Critical filter.